Question 1
During indoor-camera pre-wire, a client requests an additional gate camera requiring a new trench and conduit. The signed scope excludes this work. Indoor cabling can proceed independently, and the project manager must authorize scope, cost, and schedule changes. How should the technician keep authorized work moving?
Show answer & explanation
Correct answer: C - Continue indoor cabling and submit the gate-camera change for authorization.